Projects

Gerba South Wollo Amhara Region Ethiopia
Project Name: Supply and installation of Solar system
Project Objective: To install Solar System to off grid rural community
Tasks:
- Mounting Solar PV Panels
- Mounting Charge Controllers
- Connecting the cables
- Connecting batteries
- Load Test and Documentation
Project Duration: 4 Weeks

Kemisse South Wollo Amhara Region Ethiopia
Project Name: Design Construction and Installation of an automatic Solar powered water pumping, delivering and distribution system
Project Objective: To install a water system to supply water to a community home use and irrigation
Tasks:
- Site visit and water pump selection
- Carryout a pump and recovery testing(24hrs constant) including water quality test
- install a steel tank tower to support two tanks of 5000 litters each 6 meter high
- Construction pump protection unit and tap stand
- Design and Install Solar powered water pumping system
Project Duration: 12 Weeks

Prosperity Party building Addis Ababa Ethiopia
Project Name: Design, Supply and Installation of Hybrid power backup system
Project Objective: To install hybrid 15KVA power backup system for G+10 building
Tasks:
- Wiring power cables for each floor
- mounting distribution board( MDB & SDB)
- Connecting batteries
- mounting Solar PV Panels to charger controller
- Load Testing and Documentation
Project Duration: 2 Weeks

Abyissina Steel Debrezit Oromia Ethiopia
Project Name: Design, Supply and Installation of Hybrid power backup system
Project Objective: To install hybrid different size power backup system for factory site
Tasks:
- Site survey and path selection for cabling
- Wiring power cables for the selected path
- mounting distribution board( MDB & SDB)
- Connecting batteries
- mounting Solar PV Panels on factory site
- connecting Solar PV panels to charger controller
- Load Testing and Documentation
Project Duration: 12 Weeks